NFPA 110: Standard for Emergency and Standby Power Systems extended Q&A
Q: When is it required to have a 3 pole and 4 pole ATS?
Q: With respect to breaker coordination; what are the preferred electronic trips: LI, LS/I, LSI, or LSIG?
Q: Do you recommend dual hot-standby control PLCs when installing parallel gensets?
Q: Are schools considered to be Level 1 or Level 2 facilities? Typically, Level 1 is needed for health care or mission critical facilities only.
Q: What is the intent/purpose of physically separating the critical branch and life safety branches? Can one have a detrimental impact on the other?
Q: Is mineral-insulated (MI) cable needed for optional standby generator feeder circuits?
Q: Does the 10-second power restoration start time apply to the main service or to the end use device?
Q: Does the emergency system include conductors and other equipment upstream from an ATS on the normal side of the ATS?
Q: Should the emergency service switchboard that feeds the ATSs be in a separate room from the room that contains the ATSs?
Q: If the only important issue is egress lighting, can that be addressed with battery lights, and if so, can my system be standby only?
Q: When referring to the NEC as related to the EPSS, do you need to also consider article 695 elevators and 517 hospitals for additional requirements?
Q: How long does the crank test need to be done on the generator?
Q: Is the use of closed transition transfer switches recommended for Level 1 facilities? Any issues with using closed transition switches?
Q: What are the requirements for the life safety and critical branch systems when the building—specifically a skilled nursing facility—has a full building backup generator? Do you still require separate ATSs, even though we have separate panels and wiring within the building? Contractors feel this is not needed.
Q: If I have a system per Article 701 and Article 702 application, what branches do the battery charger, fuel pump, and dampers get connected to?
Q: If a hospital is to be 100% backed up by Generators, is it a violation of NEC 517.30(B)(4)-Transfer Switches to eliminate all transfer switches by providing Medium Voltage Generators and tie them thru a paralleling gear to a Medium Voltage Distribution Switchgear at the Central Utility Plant? Transfer of power will be at the Medium Voltage switchgear.
Q: Could the 517.34 system be considered as a 701 system?
Q: To test under on-site or portable load bank, do facilities have a TESTING transfer switch to connect the load bank to the system and provide that auto removal of load bank if utility power fails during load bank testing?
Q: Can you combine Article 700-type loads and Article 701-type loads within the same switchgear and on the same OCPD of a generator?
Q: While performing the 2 hour load test per 7.13.4.3, I assume the generator OEM factory can perform only a 2 hour reactive load test at rated power factor to comply with 7.13.4.3.2, correct?
– Edited by Jessica DuBois-Maahs, associate content manager, CFE Media, jdmaahs(a)cfemedia.com.
Do you have experience and expertise with the topics mentioned in this content? You should consider contributing to our CFE Media editorial team and getting the recognition you and your company deserve. Click here to start this process.
Lenexa, US
Peachtree City, US
Westminster, US
Duluth, US
Evansville, US
Tom Divine:Kenneth Kutsmeda:Kutsmeda:Divine:Kutsmeda:Divine:Kutsmeda:Kutsmeda:Divine:Kutsmeda:Kutsmeda:Divine:Kutsmeda:Divine:Kutsmeda:Divine:Kutsmeda:Divine:Kutsmeda:Divine: